Phase rotation, or mismatch of voltage and amperage measurement, is a problem that occurs when the source of the voltage connections on the meter is different from the source of the amperage connections.
Example, voltage measurement order is Red | White | Blue
and amperage (CT) measurement order is White | Red | Blue
- Symptoms:
- Unbalanced power factor between phases:
Ideally you would want the power factor between the 3 phases to be relatively close to each other.
Example pfa 0.9125 | pfb 0.9298 | pfc 0.9098 - This would be normal.
As per the image below, when a large difference on one or two of the phases exists, it is worth testing. - All phases show very low power factor:
Where you have a 3 phase mismatch, it could be possible to see very low readings on all three phases.
Example pfa 0.3165 | pfb 0.3087 | pfc 0.3258
This would necessitate on-site testing to find the problem. - "Jumping" polarity:
In some cases, phase rotation could cause polarity on one or more phases to jump between positive and negative readings. Assuming that the "Polarity Issues" have been checked, this could indicate a phase rotation and needs to be tested on-site.
When trying to correct an incorrect polarity where a phase rotation exists, polarity will jump around, not corresponding to the changes being made on site.
- Testing & Correction of the issue:
An on site, qualified technician is required on site in order to perform the following test.
- Trace the red phase, CT secondary wires, from the red phase CTterminals on the meter, to the actual Cable/busbar that the CT is connected to.
- Confirm that the CT is visually correct on the red phase
- Place one end of the multimeter on the red phase primary cable terminal/busbar.
- Place the other end of the multimeter on the red phase voltage terminal of the meter.
- Ask the technician what the voltage reading is.
- If 0v, then the source of the 2 points are the same.
- The same test needs to be done on the white and blue phases.
- If all 3 measure 0v, then there is no phase rotation.
- If 400v, then the source of the voltage and CT is not the same.
- Now this same test needs to be done on the white and blue phases.
- Depending on if this is a 2 or 3 wire rotation/mismatch, the technician on site should use this testing method to find common sourced phases.
- The voltage connections on the meter should then be changed until the test can be completed, measuring 0v on all three phases.
- Note:
- These symptoms and testing methods only apply to low voltage (230/400v) installations.
- MV installations need to be tested on site if phase rotation is suspected.
- This would be indicated by a very low total PF when looking at the demand/power chart.
- Testing of MV installations are much more difficult, since the MV side in generally not accessible from the metering room. This means that a shutdown would be needed in order to allow for the electrician to trace wires.
- These instructions should be given very clearly as it is very common for technicians to do what they think is correct, instead of following instructions.